Here is a running timeline of our build:
January 2016
January 3- Visited 2 models on a whim. We wound up sitting down and pricing up a house!
January 7- Signed our contract!
January 14- Phone meeting for our NVR meeting (due to weather)
January 21- 14-day meeting (final structural changes)
January 21- NVR meeting to sign paperwork.
January 28- Coleman flooring appointment
February 2016
February 4- Trinity Wiring appointment
February 4- 30-day meeting (no more changes)
March 2016
March 17- Pre-Construction Meeting!
March 24- Ground Breaking
March 28- Footers poured
March 30- Foundation walls
April 2016
April 11- Basement slab poured
April 12- Lumber delivery
April 13- First floor framed
April 14- Second floor and roof framed
April 16- Windows installed
April 21- House walkthrough for Trinity placement (we requested this)
April 26- Rate Lock
April 26- Rate Lock
April 28- Pre-Drywall meeting
April 29 & 30- Insulation
May 2016
May 2- Insulation Inspection
May 3- Drywall begins
May 11- House trimmed
May 16- Siding Finished
May 20- Walkthrough- Cabinets & appliances installed, painting mostly complete, final electrical complete, some flooring
May 23- Granite & Carpet Installed
May 25- First coat of paint on front door; driveway apron and sidewalk poured